Chennai Metro Rail Limited has completed the launching of all U-girders on the Koyambedu-Alandur stretch of its phase II project, according to a press release. The corridor, which runs for 14.5 km under the 118.9-km phase II project, is scheduled to be opened next year, and track work on the stretch is also in advanced stages.
U-girders are precast concrete structural beams used in the construction of elevated viaducts, over which trains run. The final girder on the stretch was launched on Sunday between Butt Road and Kathipara Junction over Paul Wells Road, using two high-capacity hydraulic cranes. The completed stretch comprises 911 U-girders, ranging in length from 15 metres to 33.33 metres, with an average girder weight of approximately 135 tonnes, the release said. Erecting works were carried out using multiple methodologies, including launching girders and high-capacity hydraulic cranes, depending on site conditions and the requirements of each location.
The release said the elevated construction work faced several challenges, including space constraints and underground and overhead utility lines at locations such as Kaliamman Koil Street, Butt Road and Paul Wells Road. The integrated flyover along Mount-Poonamallee Road further added to the complexity, making the girder launching operations particularly challenging.
The last U-girder erected on Sunday at Paul Wells Road proved challenging owing to a space crunch, with one of the two high-capacity cranes positioned within the nearby church premises and the other placed within a narrow street, the release said. For another U-girder at the same location, the Metro Rail had to mobilise another 1,000-tonne-capacity crane to finish the work in a tight time frame with very limited space.