The slow pace of work on the Dr. B.R. Ambedkar Bhavan in Mysuru has been blamed on a lack of coordination among the contractor, the project supervision consultants and the architectural staff. The matter was discussed at a meeting chaired by Commissioner of Mysuru Development Authority (MDA) Islauddin J. Gadyal on Wednesday, which followed complaints about the delay.
According to an MDA statement, the contractor and the project supervision consultants were instructed to resolve their differences and misunderstandings so that the project could be completed early. MDA officials and the contractor were also directed to prepare a checklist of pending works and fix specific timelines for each, in line with a 'Programme of Works with Bar Chart', to ensure completion within the stipulated period.
The architectural staff were asked to prepare the necessary design drawings, obtain approval from the Authority and provide them to the contractor and consultants in a timely manner. The contractor has been directed to complete all pending works by January 26, 2027, while ensuring quality construction in accordance with the drawings and project cost estimates.
The meeting was attended by MDA officials, the contractor, project consultants, architectural staff and leaders of Dalit organisations. The development comes after Minister in-charge of Mysuru district Yathindra Siddaramaiah recently held a meeting with officials following complaints about the non-completion of works on the Bhavan.