The Greater Chennai Corporation (GCC) has relaxed conditions for its 2026-27 road relaying contracts and will issue work orders through the Tamil Nadu government's e-procurement portal, hosted by the National Informatics Centre, according to a GCC official. The changes are aimed at widening contractor participation and curbing cartelisation of bidders.
Under the new procedure, work orders will be generated online once financial bids are opened, negotiations are completed and letters of acceptance are issued, so contractors need not approach officials separately for the document required to begin execution. The GCC has also revised rules on additional security deposits: only the lowest bidder must furnish the deposit, within two days of the first negotiation, through NEFT, RTGS or an electronic bank guarantee. Previously the requirement applied at the tender-opening stage; the change is intended to protect the confidentiality of financial bids, the official said.
Bidders may now use owned or registered leased centralised hot mix plants with a valid consent to operate certificate from the Tamil Nadu Pollution Control Board, located within 40 km of the GCC boundary. They can participate in more than one package if they meet eligibility conditions. The works cover 753 roads across all 15 zones, including 66 bus route roads, spanning 167.55 km, of which 43.86 km are bus route roads. The estimated cost is ₹149.12 crore, including ₹68.31 crore for bus route road works. Tenders are scheduled for November 27, December 3 and 7, 2026.
The GCC will retain 2.5% of the contract amount during the three-year defect liability period as a safeguard against defects, the official said; contractors will be responsible for rectifying defects during this period and can replace the withheld amount with an e-bank guarantee after completing the work. The provision is meant to guard against contractors quoting steep discounts and failing to complete works, the official said, noting that GCC tenders had generally attracted bids above the estimated cost in the past but have recently received discounts of 20% to 30% below estimates. The GCC rejected a request to relax the pollution consent requirement, citing National Green Tribunal directions, but permitted registered leased plants subject to the prescribed conditions.